The Enron Saga
Excerpts
The Power Sector
The Power Factor
The MoU between Enron and MSEB was signed prior to the examination of the terms and conditions and implication of the project. Among the parameters that should have been examined were the capital cost of the plant (on which the price of electricity depends), the type of fuel to be used, the location of the plant etc.
The Peak Load
The project generated much controversy in Maharashtra. Of the two main opposition parties (the BJP and Shiv Sena) , the BJP was in the forefront of the opposition to the project on a number of grounds. Their primary contention was that the deal indicated corruption at the highest level. In January 1995, elections to the Maharashtra state assembly were announced. Enron was made a key issue in the elections. Gopinath Munde, leader of the BJP, visited the Enron site and promised to throw "the project in the Arabian Sea". Business Line and Frontline carried long and detailed articles on the PPA, which had been kept secret up till then......
A Tripp
The MSEB's inability to pay DPC was rapidly emerging as a threat to the viability of phase II of the project which involved a generating capacity of 1, 400 MW and an LNG terminal of 5 million tons.There was an increasing possibility that the dispute over phase I might end up in international arbitration, if MSEB failed to pay up and the state government refused to bail out the ailing MSEB. The PPA had provisions for arbitration in case a dispute could not be resolved through negotiations......
Exhibit
Exhibit I: Chronology of Events
Exhibit II: Cogentrix Power Project